    Project:   Upgrading, construction and installation of 2G, 3G Viettel equipment in some Northern provinces

    Investor:   Viettel Networks Corporation - Branch of Viettel Group

    Location:  Some Northern provinces


    On November 6, 2013, at the headquarters of Viettel Network Corporation, there was a Contract Signing Ceremony No. 06.11301 / VTNet-Vinaconex6 / XL-2013 between Viettel Network Corporation and Vinaconex6 Joint Stock Company with content contract: "Expanding and upgrading the quality of Viettel telecommunications network in 2013; New construction and installation of equipment for BTS stations in 10 Northern provinces: Bac Giang, Bac Kan, Bac Ninh, Hanoi, Hung Yen, Ha Nam, Thai Nguyen, Hoa Binh, Hai Duong and Vinh Phuc ". With a contract value of 205 billion.

    Following the package above, on December 8, 2014, also at the headquarters of Viettel Network Corporation, the Signing Ceremony of Block 6 Work Construction Contract took place: "Construction and installation of equipment. 2G, 3G in 3 provinces of Bac Giang, Bac Ninh, Hai Duong "between Viettel Network Corporation and Vinaconex6 Joint Stock Company with a contract value of 42,969 billion VND.

    According to the contract, the construction progress of the Works is 500 days.

    The project is completed and put into use in early 2016.


    Pictures of the contract signing session: