Dự án
TIN TỨC
Phi Hong Vietnam Electrical and Electronic Equipment Factory (Phase 2)
Date: 2021
Chi tiết dự án
Project: Phi Hong Vietnam Electrical and Electronic Equipment Factory (Phase 2)
The Client: PHIHONG Vietnam Co., Ltd.
Location: Lot CN5, An Duong Industrial Park, Hong Phong Commune, An Duong District, Hai Phong City
Project scale:
Workshops 03 and 04 and ancillary works.
Total construction area: 16,537.5 m2
Construction floor area is 58,453.5 m2
Scope of works:
General contractor for construction of the rough part and finishing of the workshop and ancillary works
Construction schedule:
Factory 3: From May 5, 2021 to November 30, 2021
Factory 4 and sub-items: From 05/05/2021 to 02/28/2022
Dự án liên quan